A weir has a function, which is to raise the water level of the river and
drain portion of existing water flow towards the right bank and left bank of
the river to flow into the channel through a decision of the building
irrigation networks. Weir can also be defined as the waterworks were built
transversely river, so that the water level of the river in the vicinity rises
to a certain height, so that river water can flow through the channel divider
tapping into the channel and then to the agricultural lands.
A construction of a dam can be made of the land fill, masonry times, and
gabion or concrete. A weir construction is made transverse river and its main
function is to stem the flow of the river and raise the level or rate of water
level upstream.
The terms of dam construction must meet a number of factors, namely
• weir must be stable and able to withstand water pressure at the time of
the flood;
• Making the weir should take into account the strength of the carrying
capacity of the ground beneath it;
• weir should be able to withstand leakage (seepage) caused by the flow of
river water and streams of water that seep into the soil;
• High weir sill must be able to meet the minimum water level required for
the entire irrigation area;
• Form peluap must be taken into account, so that water can carry sand,
gravel and stones from the upstream and does not cause damage to the body weir.
Dam construction site selection should be based on several factors, namely
• The state of Topography
o In this case all planned irrigated areas can be irrigated, so it must be
seen to be the highest elevation diary rice;
o If the highest elevation that will be irrigated rice fields have known
the lighthouse weir elevation can be set;
• From both of the above, the location of the dam in terms of topography
can be selected.
• The state of Hydrology
In the manufacture of the weir, which is also a factor to be reckoned with
- hydrological factors, because it determines the width and length of the dam
and weir height depending on discharge plan. Factors - factors that are taken
into account, namely the problem of flooding plan, calculation of discharge
plans, effective rainfall, rainfall distribution, unit hydrograph, and flooding
in the site or weir.
• Topography Conditions
Judging from the location, the dam must consider several aspects, namely
o The height of the weir is not too high.
o Trace trunk is located in a good place.
• Hydraulic conditions and Morphology
o river flow patterns include speed and direction at the time of the flood
discharge;
o The depth and width of the water level at the time of the flood
discharge;
o The water level in the flood discharge plan;
o Potential sediment transport and distribution.
• Foundations Soil Conditions
Weir must be placed in a location where the soil foundation is good enough
so that the building will be stabilized. Another factor that must be considered
also the potential for seismic and potential scour due to currents and so on.
• Implementation Costs
The cost of implementation of dam construction has also become a
determining factor for the selection of dam construction site. From several
alternative locations also in terms of the least expensive in terms of cost and
implementation is not too difficult.
Here is a method of making a weir:
1. Preparation of the dam began with the manufacture of diversion channel
(channel diversion) built on the right side of the river
2. The work began with the work on the diversion work by digging the soil
and manufacture of dykes to divert the river flow. After the diverted river dam
site can be drained through the dewatering process.
Pictures river flow diversion
3. Furthermore weir work continued with the excavation work and the results
of excavation excavator transported by dump truck to be discharged to the
disposal area or kept as stock for embankment material according to soil type
and specification.
Picture excavation work
4. When you encounter the bedrock excavation, rock excavation work done
5. Selected methods of drilling and blasting, which is on the surface of
the rock made blasting pattern. Then make a hole with a rock drill (cradler
rock driller) or canal drilling
to fill a number of explosives (Dynamit) and detonator as a trigger
Pictures work on hard ground
6. After blasting, excavation proceeds collected by the excavator and dump
truck transported to disposal area
7. Excavated rock by blasting (blasting) is usually difficult to form the
basis of the neat suit excavation rock excavation existing line in the shop
drawing
8. Next use giant breaker mounted on excavators for shaping and smoothing
rock excavation
9. Before the foundation of the dam began concrete work, work to be done is
finishing rock surface by cleaning up all loose material and seal the surface
with a splash grouting.
10. Splash grouting cement is a mixture of sand and water is poured over
the surface of the rock
Pictures splash grouting work
11. The next stage is concrete work (concrete) for the foundation, the body
weir, eddy pool (stilling basin) and the piers and column
12. On the surface friction occurring weir on the river water where it is
assumed there are loose rocks, twigs and tree, therefore it needs to be lined
with steel fiber concrete
13. In the motion made weir hoist room building that is a driving machine
door, mounted in the form of a pulley (hoist) electrically to raise and lower
the door
Hoist room weir motion picture
14. After the main part is done, followed by the building and the apron
floor stilling basin floor which followed the work of the backfill with
selected material (selected embankment)
15. Bridges made a separate ministry for use in the fabrication of precast
prestressed concrete, which was launched by launching method trus
16. The main civil works of the most severe is the manufacture and hoist
pier deck, because it requires high precision and accuracy in order to
interfacing with the work doors (hydro mechanical) not a lot of difficulty
17. In determining the use of formwork scaffolding on the floor hoist room
need special handling because at a height of 28 m, should do the job with a
load of hundreds of tons of concrete and sizeable deflection
Image sequence weir body work
Picture mounting pillars movable weir and king shore hoist insertion deck
18. Implementation of the motion weir and dam remains a critical path.
While work apron, stilling basin and Fishway job is not critical but can be implemented
in parallel with the work of appropriate capacity to provide concrete dam per
day
19. For the manufacture of concrete pier and column used climbing formwork
with two types, namely to wear arch and steel formwork for straight used wood
and plywood formwork
Image-making pier and concrete columns
20. During the implementation phase pengecoranbeton to the pier there are
two types of concrete which should be carried out jointly to avoid connection
(cold joint) is between ordinary concrete and concrete mixtures tons of steel
fiber mix
21. For both types of concrete are not mixed, use chicken wire on hold with
iron rods or wire mesh
22. Pengecorannya performed alternately in a relatively the same between
steel fiber concrete and ordinary concrete
23. Proceed with casting parts in elevation above and in accordance with
the height of climbing formwork
Pictures casting pier and concrete columns weir
24. To hoist room building walls that originally was ordinary concrete,
made innovations into the column and beam steel frame with precast prestressed
wall panels (hollow core wall) for walls and roof plate.
No comments:
Post a Comment